
The 500-acre site on Ghana's harbour corridor.
Land, legals, engineering and capital sequenced into one execution path: Phase-1 acquisition in 2026, EPC across 2027–28, and first green steel pour planned for Q4 2028.
One contiguous Phase-1 parcel.
Phase-1 footprint sized for generation, hydrogen, steelmaking and logistics on one contiguous site.
Proximity-to-harbour route for feedstock imports and green steel export.
Parcel due diligence and Phase-1 securing under the 2026 workstream.
Structured with national and traditional authorities under Ghanaian land law.
The consenting path, workstream by workstream.
Parcel searches, boundary survey, tenure documentation and registration of the Phase-1 holding.
ESIA scoping and submission, resettlement and community engagement framework, IFC-aligned safeguards.
Construction, water abstraction, generation licensing and industrial operating permissions.
Molten Oxide Electrolysis licensing commenced under the 2024 technology-stack milestone.
Interconnection, hydro dispatch contracting and offtake heads of terms.
Owner's engineer appointment, package tendering and EPC award ahead of mobilisation.
Consenting is sequenced so that no construction package is awarded ahead of its enabling permit.
From mobilisation to first pour.
- 2026
Site & logistics commencement
- Phase-1 land secured
- Surveys, geotech and ESIA
- Access roads and site establishment
- Owner's engineer and EPC tendering
- 2027 H1
Mobilisation & earthworks
- EPC award and site mobilisation
- Bulk earthworks and platform levelling
- Substation and collector network civils
- Long-lead equipment ordered
- 2027 H2
Generation & process erection
- First solar blocks energised
- Turbine erection begins
- Electrolyser and DRI-EAF foundations
- Water and utilities backbone
- 2028 H1–H3
Mechanical completion
- Tri-source generation integrated
- Hydrogen block commissioned
- EAF and MOE installation complete
- ASIS orchestration commissioning
- Q4 2028
First green steel pour
- Hot commissioning and first pour
- Product qualification runs
- Ramp planning toward 3M MT capacity
- Carbon accounting baseline locked
How capital to first pour is structured.
Captive generation
500 MW solar, wind, hydro interconnection and battery storage.
Process islands
Electrolysers, hydrogen storage, DRI-EAF and MOE units.
Site & logistics
Earthworks, roads, rail spur, water, laydown and harbour-route works.
Digital layer
ASIS orchestration, SCADA/EMS integration and the Nibble OS control estate.
Owner's costs & contingency
Development, legal, insurance, interest during construction and contingency.
Committed values, drawdown profile and contingency levels sit in the financial model. Institutional investors can request it through the data room.
Request the financial model